SÓLIDA is awarded the owner’s engineering of a 234 MW photovoltaic cluster in Cádiz

The project, promoted by Statkraft, consists of 4 photovoltaic plants and their electrical evacuation infrastructure.

The project, promoted by Statkraft, consists of 4 photovoltaic plants and their electrical evacuation infrastructure.

SÓLIDA Renewable Energy has won the tender for the owner’s engineering of a photovoltaic cluster located between the municipalities of Jerez de la Frontera and San José del Valle, in the province of Cádiz.

The Project consists of the PV plants Arenosas, El Yarte, La Guita & Malabrigo, that sum up a total power of 234 MW. The contract includes as well the electrical infrastructure made of 4 mid-voltage lines, a booster station 30/132 kV, a 132 kV line and the new bay of the transformer in the existing Valle I substation to which the plants will be connected.

Statkraft, which recently acquired Solarcentury with its entire pipeline under development, has once again trusted SÓLIDA as a technical partner in a project whose construction is expected to last 14 months and employ more than 500 people.

This contract strengthens SÓLIDA as a reference in this type of service, where experience and knowledge are combined with the ability to adapt and solve increasingly complex problems, with the aim of guaranteeing that the projects meet the client’s quality standards. in time and form.