Client:
Villanueva de los Escuderos Node
400/132 kV
Cuenca
, Spain
AIE Escuderos
Project’s scope:
Permitting Project and Owner's engineering for substation and line.
Description:
- Grid Connection Project (+750 MW Wind &PV)
- Executive Technical Project for Permitting.
- Technical support for transformer procurement (780
MVA). - EPC contract management.
- Substation and line Detailed Engineering review.
- FAT tests Supervision.
- Quality, planning and certifications control.
- Project management.