Campanario Renovables Node

  • Type of project : Grid connection infrastructure for renewables
  • Substation : 132/400 kV
  • Transmission line : 0,5 KM 400 KV

 

780 MVA
2019
Albacete
, Spain

Client:

Capital Energy, Cobra, Elawan, Grupo Zaragozá, Rotonda

Project’s scope:

Permitting Project and Owner's Engineering Substation and Line.

Description:

  • Grid Connection Project (+750 MW Wind & PV)
  • Executive Technical Project for Permitting.
  • Technical support for transformer procurement (780 MVA).
  • EPC contract management.
  • Substation and line Detailed Engineering review.
  • FAT tests Supervision.
  • Quality, planning and certifications control.
  • Project management.

See other technologies cases